Retainage Calculator — by Line Item, by Pay Period, and at Substantial Completion

By PayAppKit Editorial Team

See how much is held, what changes this period, and the effect of an approved release. Set work and stored-material rates separately.

LIVE WORKSHEET / Your pay application
Oak Street OfficesElectrical subcontract · USD · Original contract $100,000.00
G703 Schedule of ValuesInstalled % excludes stored materials
DESCRIPTION / SOVINSTALLED %STORED $HELD %COMPLETED + STORED
01
Scheduled $10,000.00
$10,000.00Retainage $1,000.00
Line 01 · previous period, rates & release

Reduction applies to all completed work on this line once installed work reaches 50%; stored-material rate stays separate. Use only contract-approved reductions and releases.

02
Scheduled $40,000.00
$20,000.00Retainage $2,000.00
Line 02 · previous period, rates & release

Reduction applies to all completed work on this line once installed work reaches 50%; stored-material rate stays separate. Use only contract-approved reductions and releases.

03
Scheduled $30,000.00
$12,000.00Retainage $1,200.00
Line 03 · previous period, rates & release

Reduction applies to all completed work on this line once installed work reaches 50%; stored-material rate stays separate. Use only contract-approved reductions and releases.

04
Scheduled $15,000.00
$1,500.00Retainage $75.00
Line 04 · previous period, rates & release

Reduction applies to all completed work on this line once installed work reaches 50%; stored-material rate stays separate. Use only contract-approved reductions and releases.

05
Scheduled $5,000.00
$0.00Retainage $0.00
Line 05 · previous period, rates & release

Reduction applies to all completed work on this line once installed work reaches 50%; stored-material rate stays separate. Use only contract-approved reductions and releases.

Add a change order

Calculations stay in this browser tab. Download before leaving.USD · rounded by line to the cent

How the retainage calculation works

For each line, held retainage equals completed work × work rate, plus presently stored materials × stored rate, minus an approved release. Previous certified value equals previous work + previous stored materials − previous retainage.

Rate reduction at 50% installed completion

Enable the line option only when approved for your contract. This model halves the work rate on all cumulative installed work at 50% installed completion. It leaves the stored-material rate unchanged. This is an explicit modeling choice; use the rates required by your contract.

Substantial completion release

Open a line’s details and enter the release amount or choose “Release all held on this line.” A release increases cumulative earned less retainage and the current amount due. The tool flags a release larger than the amount held. Substantial completion does not itself authorize a release.